Complex gas treatment plant

We have successfully completed the development of a working design for the installation of a complex gas treatment plant (CGTP). The design includes the following components and elements:

  1. Main process parameters:
  • CGTP productivity for raw gas 1,053 mln.nm3/day (at Т=0 ºС, Р= 0,1013МPа).
  • Gas pressure at CGTP inlet: 5,2 … 7,6 МPа.
  • Designed inlet pressure: 10 МPа
  • Gas temperature at CGTP inlet: minus 8,8 ºС…+40 ºС.

2. CGTP production:

  • Treated and dried gas in main gas line – 35920 nm3/hour (287,36 mln.nm3/year).
  • Stable gas condensate – 1354 kg/hour (10,832 thous. t/year).
  • Technical propane-butane – 6842 kg/hour (57,74 thous. t/year)
  • Sulphur lumps – 3262,75 kg/hour (26102 t/year).

3. CGTP composition:

  • Inlet manifolds and primary gas separation unit (PGSU).
  • Low-temperature gas separation unit (LTGSU).
  • Amine desulphurization unit (ADSU).
  • Boosting compressor station (BCS).
  • Sulfur production unit (SPU).
  • Condensate stabilization unit (CSU).
  • Heat carrier heating unit (HCHU).
  • Compressed air and nitrogen production unit.
  • Fuel gas treatment unit.
  • Flare system.
  • Condensate tank farm.
  • Propane-butane tank farm.
  • Methanol tank farm.
  • Installation of industrial effluents disposal.
  • Amine storage.
  • Sulfur lumps storage.
  • Laboratory.
  • Administrative and service building with operator room.
  • RMW.
  • 2 SCP.
  • HFL and precursors.
  • 2 reserve DES.
  • Switchgear 6kV.
  • Industrial and fire-fighting water supply pump house.
  • Fire-fighting water supply tanks.
  • Circulating water supply unit.
  • Local treatment facilities.
  • Vehicle scales.
  • Service lines and auxiliary equipment.